When our charging station construction project is determined, we will proceed through the two parts of the National Development and Reform Commission and the power Supply Bureau, and the following will be understood with the charging pile manufacturer Jingneng New Energy.
First, the NDRC project filing
1. Project detailed address;
2. Project cooperation agreement;
3. Specific planning of the construction of charging stations;
4. The Project Feasibility Study Report shall be issued by a consulting company with consulting qualification;
5. Provide the approval certificate of the construction authorities above the district level (development, reform, letter, planning), in the form of a government stamp on the customer's information statement to prove the legality of the project;
6. Enterprise qualification and other materials required by NDRC.
Two, high pressure installation
1. Electricity application;
2. Enterprise qualification and other materials required by NDRC;
3. Power of attorney;
4. Provide the approval certificate of the construction authorities above the district level (development, reform, letter, planning), in the form of a government stamp on the customer's information statement to prove the legality of the project;
5. Design Institute qualification (Design institute registered in the local power supply bureau, consult the power supply bureau when applying, seal);
6. Design institute drawings (according to the requirements of each power supply bureau to provide corresponding copies);
7. Transformer effect test, table to calculate the installation cost.
Three. Design the drawing
1. "Power Supply Scheme Reply";
2. Design and survey;
3. Charging station construction blueprint (as needed to determine the number of copies);
4. Design institute qualification (seal);
5. Design the contract.