General flow of charging pile installation and construction

Views : 1023
Update time : 2025-04-14

Once the two sides reach cooperation and sign the contract advance payment, after the charging pile manufacturer completes the commissioning of the equipment, the next step is the installation process of docking the construction team to the site for equipment installation. Below, we will take a look at the general process of the construction team entering the construction site.

General flow of charging pile installation and construction

First, high-pressure construction

1. Power supply down point (down pole number or ring network unit number);

2.SOG circuit breaker model;

3. Wire, arrester model;

4. Isolation knife model, specification;

5. Wire and cable type, specification, length, laying method;

6. Pole type, specification, quantity;

7. Metering device installation method (column measurement, box change measurement);

8. Outlet mode of box variable high pressure (ring network type, terminal type);

9. High-voltage inlet cabinet circuit breaker, metering cabinet, outlet cabinet product model and configuration;

10. Transformer model and air cooling mode (oil change, dry change);

11. Low-voltage circuit breaker model, brand, quantity, specifications, etc.;

12. Capacitance, quantity, specifications, etc., in the low-voltage capacitor cabinet;

13. Case change and foundation construction drawings.

Two, low pressure construction

1. Size drawing, direction drawing and construction drawing of cable trench;

2. Production drawing and quantity of cable support;

3. Cable trench cover plate drawing, cover plate number;

4. Canopy film structure construction drawing, foundation embedded parts drawing;

5. Grounding system drawings, mainly box conversion, cable support grounding, charging pile grounding, membrane structure grounding, etc.;

6. Construction drawing of charging pile foundation;

7. Lighting system installation drawing and configuration;

8. Monitoring system installation diagram and configuration;

9. Parking lines, blockers and anti-collision guardrail construction drawings;

10. Charging station billboards, guide boards, LED signs.

Iii. Completion acceptance

Content of completion report:

1. Completion information provided by the construction party;

2. Application materials of local NDRC;

3. As-built drawings;

4. Acceptance report of power supply bureau;

5. Prepare relevant documents according to local approval procedures.

Related News
Read More >>
How long does it take to charge an electric car ? How long does it take to charge ···
2024-09-23
How long does it take to charge an electric car? In this article we will consider the time to charge for domestic charge···...
DC Fast Charging CCS type 2 plug DC Fast Charging CCS type 2 plug
2024-09-23
Shanghai Mida Electric Vehicle Power Co., Ltd. is a well-known brand that produces numerous electric vehicle products in···...
The high-voltage and high-current supercharging pile is the future development trend of the world The high-voltage and high-curren···
2024-11-22
Trend 1: V2G Technology and "virtual Power Plants"Virtual power plant is not a power station in the real sense···...

Leave Your Message