Once the two sides reach cooperation and sign the contract advance payment, after the charging pile manufacturer completes the commissioning of the equipment, the next step is the installation process of docking the construction team to the site for equipment installation. Below, we will take a look at the general process of the construction team entering the construction site.
First, high-pressure construction
1. Power supply down point (down pole number or ring network unit number);
2.SOG circuit breaker model;
3. Wire, arrester model;
4. Isolation knife model, specification;
5. Wire and cable type, specification, length, laying method;
6. Pole type, specification, quantity;
7. Metering device installation method (column measurement, box change measurement);
8. Outlet mode of box variable high pressure (ring network type, terminal type);
9. High-voltage inlet cabinet circuit breaker, metering cabinet, outlet cabinet product model and configuration;
10. Transformer model and air cooling mode (oil change, dry change);
11. Low-voltage circuit breaker model, brand, quantity, specifications, etc.;
12. Capacitance, quantity, specifications, etc., in the low-voltage capacitor cabinet;
13. Case change and foundation construction drawings.
Two, low pressure construction
1. Size drawing, direction drawing and construction drawing of cable trench;
2. Production drawing and quantity of cable support;
3. Cable trench cover plate drawing, cover plate number;
4. Canopy film structure construction drawing, foundation embedded parts drawing;
5. Grounding system drawings, mainly box conversion, cable support grounding, charging pile grounding, membrane structure grounding, etc.;
6. Construction drawing of charging pile foundation;
7. Lighting system installation drawing and configuration;
8. Monitoring system installation diagram and configuration;
9. Parking lines, blockers and anti-collision guardrail construction drawings;
10. Charging station billboards, guide boards, LED signs.
Iii. Completion acceptance
Content of completion report:
1. Completion information provided by the construction party;
2. Application materials of local NDRC;
3. As-built drawings;
4. Acceptance report of power supply bureau;
5. Prepare relevant documents according to local approval procedures.